FLMK – Kamwingi Church Construction

 

IMG_2566

Land was purchased July 2014 and Kamwingi Church was birthed. The congregation has grown slowly, but steadily to over 30. They worshipped under a tree initially for 3 months. The congregation then purchased a tarp and built a temporary building where they have been worshipping, teaching, training and the Word has been preached each Sunday. This past December, they set a goal to make the 5,000 bricks necessary to help build a permanent building. In October they accomplished their goal!

     Our Kamwingi congregation has vision and are willing to labor for Christ. They have now outgrown their wood pole structure and need more room. What they need is what they cannot give. The balance of what is needed to build a 25’ x 30’ brick church is below.

Metalsheets 3mtr 24 740 17760
Metalsheets 2mtr 24 540 12960
Cement / bg 65 850 55250
Timber 4×2 124 45 5580
Timber 3×2 300 37 11100
Ordinary Nails 2″3″4″ / kg 11 200 2200
Y12 Iron Rods 12 1000 12000
R6 Iron Rods 6 350 2100
Roofing Nails / kg 5 200 1000
Hoops (misomo) / kg 3 200 600
Rages 8 230 1840
Doors(Metal) 2 8000 16000
Frame / ft 34 46 1564
Sand / wlb 240 60 14400
Concrete / wlb 80 80 6400
Ballast(kakoto) / wlb 60 80 4800
Transport and Water 50,000
Labour 90,000

Total cost (305,454kshs) approx. $3,300