Mailisaba church began in July 2014 as a home church with 4 people. A 12’ x 24’ canvas and pole structure was built when they reached 24. Continuing to grow into 40+ we built a larger structure with iron sheets for a roof measuring 14’ x 42’. In the fall of 2015 the congregation was averaging 55+ and plans were made to build a permanent building on land the ministry had purchased. In February 2016 the 65+ congregation moved into their new 30’ x 70’ pole barn Worship Centre!
The congregation as of the beginning of April is averaging over 75 each and every week. To God be all the glory…
It is exciting to see this congregation continuing to grow both numerically and spiritually! The next stage of construction is building the walls.
Bricks | 14,000 | 10 | 140,000 |
Cement / bg | 110 | 800 | 88000 |
Dumb Roof Paper | 1 | 5000 | 5000 |
Timber for lendors (qnt.) | 1 | 10,000 | 10000 |
Sand / lorrie | 8 | 12,000 | 96000 |
Concrete / lorrie | 4 | 12,000 | 48000 |
Y Twisted bars | 40 | 550 | 22000 |
R 6 Bar | 20 | 300 | 6000 |
Binding Wire / kg | 10 | 150 | 1500 |
Nails / kg | 10 | 200 | 2000 |
Labour | 120,000 |
Total cost (538,500kshs) approx. $5,700 USD